11 km of an underground urban infrastructures tunnel along Haifa, from the Vulcan intersection all the way to the city’s southern entrance. The tunnel is constantly monitored for leaks and soil and water contaminations, it features defenses against inside and outside threats and is designed to operate during emergencies as well. In addition, the tunnel will facilitate the future installation of infrastructures with no disturbances to the surrounding and the on-going maintenance of the lines going through it, which would extend infrastructures’ life expectancy.

Location /
Client /
Yefeh-Nof, Foyerstein Gazit
Built Area /
520 dunam
Scope /
166,500 square meter
Status /
Deposited (not promoted)
Participants In Project /
Architect Dorit Spinat, Architect Einat Mendelson, Architect Adi Reich Roman